Las Vegas Athletics Stadium Construction: Where It Stands in October 2026

August 16, 2026  •  Updated October 15, 2026  •  The LV Athletics  •  3 min read

As of October 15, 2026, construction on the A's Las Vegas ballpark is on schedule. Crews completed the third and tallest steel roof truss arch on October 7, the team has paid for nearly $700 million in work so far, and the Review-Journal reports a February 29, 2028 completion date ahead of the 2028 season.

This is our status check on the construction site itself. For the full milestone list, see our A's stadium opening timeline, and for photos we took from the Strip on October 3, see our Las Vegas ballpark photo guide.

Construction Status (as of October 15, 2026)
  • Schedule: on time for a February 29, 2028 completion, per the Review-Journal.
  • Roof: the third steel truss arch, the tallest point of the building, was completed on October 7, 2026.
  • Spending: nearly $700 million in work completed and paid for by the team as of late September 2026.
  • Total cost: about $2.1 billion.
  • Builder: Mortenson-McCarthy.

What Has Been Built So Far

Work started with the groundbreaking on June 23, 2025, and the team said foundation work was complete in February 2026. By May 2026, the Associated Press reported the lower bowl and lower suite level taking shape, with the upper deck going up since April. In August, crews set the second steel roof truss arch, and Mortenson-McCarthy project director Tyler Van Eeckhaut called it the start of a tremendous amount of work for the coming months. On October 7, the third arch was completed, marking the stadium's highest point.

What Comes Next

Las Vegas Athletics ballpark construction with Strip resort towers in the background
The Athletics ballpark site on the Las Vegas Strip, October 2026

The next visible step is closing in the roof. Owner John Fisher told reporters in September 2026 that the roof would soon cover the facility, followed by interior work. After that come the seating bowl finishes, concourses, clubs, and the field. Construction is scheduled to wrap up on February 29, 2028.

The Money Behind the Build

The Review-Journal reported on September 29, 2026 that the price had risen to about $2.1 billion, and that the A's had covered all of the nearly $700 million in work completed so far. The team plans to start drawing Clark County public funding around mid-2027, after a bond sale. Total public funding is capped at $380 million. Our guide to the A's new Las Vegas ballpark breaks down the design and the financing.

The Plaza and Bally's

This is our status check on the construction site itself.

The ballpark sits on part of a larger site controlled by Bally's, which plans a separate resort project with an elevated plaza at the stadium's front door. In May 2026 there was talk of a temporary plaza if Bally's financing lagged. In August 2026, the Associated Press reported that Bally's said it was in the final stages of securing financing for its first phase, so the A's would not need to build a temporary setup.

Where Did the Athletics Play in 2026?

Not in the new stadium. The A's played the 2026 season at Sutter Health Park in West Sacramento, finishing 64-98, plus six regular-season home games at Las Vegas Ballpark in Summerlin in June. The 2027 plan is the same: West Sacramento, with six games in Las Vegas.

The Bottom Line

Sixteen months after groundbreaking, the A's ballpark has its tallest roof arch in place, nearly $700 million of work behind it, and a reported on-time path to a February 2028 finish. We will keep updating this page as the roof closes in.

Sources

The LV Athletics is an independent, fan-run site and is not affiliated with Major League Baseball or the Athletics organization.

Fan FAQ

Frequently Asked Questions

Is the A's Las Vegas stadium on schedule?

Yes, as of October 2026. The Las Vegas Review-Journal reported in late September 2026 that construction remains on time for a February 29, 2028 completion date.

How far along is the A's stadium construction?

Foundation work finished in February 2026, the seating bowls rose through the spring and summer, and crews completed the third and tallest steel roof truss arch on October 7, 2026. Roof enclosure and interior work come next.

How much has been spent on the A's Las Vegas stadium?

The team had paid for nearly $700 million in completed work as of September 2026, out of a total cost now reported at about $2.1 billion.

Where did the Athletics play in 2026?

At Sutter Health Park in West Sacramento, plus six regular-season home games at Las Vegas Ballpark in Summerlin in June 2026. They finished 64-98.

Where will the Athletics play in 2027?

West Sacramento again, with six more home games scheduled at Las Vegas Ballpark in Summerlin. The Strip ballpark is targeted for the 2028 season.

Who is building the A's Las Vegas ballpark?

Mortenson-McCarthy is the builder. Bjarke Ingels Group and HNTB are the architects.

Keep Reading

More Coverage

The A's New Las Vegas Ballpark: What Fans Should Know, Las Vegas Athletics stadium watch
Stadium Watch
The A's New Las Vegas Ballpark: What Fans Should Know
September 6, 2026
When Will the A's Las Vegas Stadium Open? The Full Timeline, Las Vegas Athletics stadium watch
Stadium Watch
When Will the A's Las Vegas Stadium Open? The Full Timeline
August 2, 2026
Las Vegas Athletics Stadium Update 2026: What We Know About the New Ballpark, Las Vegas Athletics stadium watch
Stadium Watch
Las Vegas Athletics Stadium Update 2026: What We Know About the New Ballpark
March 5, 2026