Stadium Watch

Who's Paying for the A's Ballpark Front Door? The Plaza Fight Explained

 •  November 16, 2026  •  7 min read

Bally's Corp. is supposed to build the plaza at the main entrance of the A's Las Vegas ballpark, but its financing is not settled. Landlord GLPI has $125 million set aside and could go to $250 million if Bally's and the A's settle open business issues; Bally's says it must start by January 2027, the A's decide on a temporary plaza in December, and the Stadium Authority meets December 3.

The A's main front door in Las Vegas is not part of the ballpark the team is building. It is a plaza that Bally's Corp. is supposed to build on its side of the site, and as of mid-November 2026 nobody has locked in how it gets paid for. The site's landlord, Gaming and Leisure Properties (GLPI), has $125 million set aside and has said it could go as high as $250 million, but only if Bally's and the A's settle a couple of open business issues first. Bally's says the plaza has to start construction by January 2027 to be ready for the 2028 opener, the A's say they will decide in December whether to fall back on a temporary plaza, and the Las Vegas Stadium Authority meets on December 3.

The Plaza Fight at a Glance (as of November 16, 2026)
  • What it is: a multilevel podium with a plaza on top at the ballpark's northwest corner, the main entrance from the Strip.
  • Who builds it: Bally's Corp., which leases the land around the ballpark from GLPI.
  • The money: GLPI has $125 million set aside and is conditionally willing to go to $250 million.
  • The catch: GLPI's funding depends on Bally's and the A's settling "a couple of business items" that have not been made public.
  • Deadlines: Bally's says it must start by January 2027; the A's need a December decision on a temporary plaza; the Stadium Authority meets December 3.

What Is the Plaza, and Why Does It Matter?

The ballpark itself takes up about 9 acres of the 35-acre former Tropicana site. Bally's controls the land around it and plans a mixed-use district with a theater and a hotel, built in phases. The first piece the A's need is the podium on the northwest corner: a three-level parking garage topped by a plaza with retail, dining and entertainment, according to project plans filed with Clark County and reported by the Las Vegas Review-Journal. Those plans put the cost of the structure at north of $200 million.

It matters because that is where most fans will walk in. Ross Bowen, the A's senior vice president of strategy and business, told the Review-Journal that 50 to 60 percent of fans will enter through the main entrance on the north side. Bally's Nick Tomasino told the Stadium Authority the plaza entry also connects the pedestrian bridges over Tropicana Avenue and the Strip.

Who Is Supposed to Pay for It?

Las Vegas Athletics ballpark under construction on the Las Vegas Strip, with steel roof arches and tower cranes
The Athletics ballpark site on the Las Vegas Strip, October 2026

Bally's. In August 2026, Bally's committed to building the podium and told the Stadium Authority it was in the final stages of securing the money, the Review-Journal reported. That financing has not come together. At a Stadium Authority meeting on November 4, Bally's was still trying to secure the funding.

That is where the landlord comes in. GLPI owns the land Bally's leases. According to The Nevada Independent, GLPI president Brandon Moore told the board the company had already set aside $125 million, money left over from the October 2024 demolition of the Tropicana, for Bally's entertainment district, and that GLPI was "conditionally willing" to increase that to $250 million. The Review-Journal quoted Moore estimating GLPI's share for the podium and related pieces at $200 million to $250 million.

What Are the "Business Items" Holding It Up?

Nobody has said publicly. Moore put it this way at the meeting: "Our funding agreement is conditioned upon a couple of business items being settled between Bally's and the A's." He called them "two critical pieces of economic impact items" and said that if GLPI is going to put $250 million into the site, "we just need to understand how the economics of that will work." The A's, Bally's and GLPI agreed the public meeting was not the place to negotiate them.

Moore also told investors on GLPI's third-quarter earnings call that the company had not committed any additional money for Bally's part of the project, The Nevada Independent reported. "We haven't ruled out some additional funding," he told the board, "but I think there's a lot that we need to see and answers that we need to have."

What Is the Deadline?

The A's main front door in Las Vegas is not part of the ballpark the team is building.

Bally's own timeline is tight. Tomasino told the board the plaza is about a 12-month build: "We would need to start by January 2027 to be able to comfortably be complete by the first quarter of 2028 and allow for the successful opening of the stadium." Bally's has some permits in and has picked Tutor Perini as its general contractor for the podium, ready to go once GLPI's money is confirmed, the Review-Journal reported.

The A's have their own clock. Sandy Dean, a senior advisor to the club, said if the team has to go with a temporary plaza, it needs to know in December so it can get permits for the escalators and elevators that would carry fans up to the main entrance. Dean said an interim plaza would need permits by June to be built in time for Opening Day 2028.

What Would a Temporary Plaza Look Like?

Lower and simpler. "We've found ourselves needing to have a contingency plan," Dean said. A temporary plaza would sit about 38 feet below the ballpark's main entrance, with escalators and elevators taking fans up to the door, the Review-Journal reported. The A's have several interim plans in different stages. GLPI saw the A's interim plan for the first time on the Monday before the meeting and would have to approve any temporary plaza, Moore said. "We're committed to making sure the A's can get into their stadium on Day 1," he said.

The A's have stepped in on site pieces before. The team previously took over from Bally's the job of building a six-story, 1,500-space parking garage and central utility plant, about $45 million of work, which crews have now started.

What Happens on December 3?

The Las Vegas Stadium Authority, the public board that oversees the project, meets on December 3 to deal with the northwest plaza entrance. Board chairman Steve Hill has said what he wants out of it: "Certainly by the meeting in December, we want to ensure there is a clear and unconditional path to make that happen." In practice, that means one of two things: a settled funding deal that lets Bally's start by January, or a temporary plaza plan the A's can permit in time.

Does Any of This Delay the Ballpark?

Not so far. The plaza is a separate project from the stadium, and the ballpark itself remains on schedule for 2028, with the Review-Journal reporting it just over 50 percent complete in mid-November 2026. Our stadium construction tracker has the latest on the roof and the shoring towers. What the plaza fight decides is what fans see and walk through on Opening Day: a finished plaza with shops and restaurants, or a temporary entrance until Bally's catches up.

The plaza money is also separate from the public money for the ballpark itself, which is capped at $380 million. Our explainer on who pays and who profits from the A's Vegas deal covers the stadium financing.

Plaza Timeline

  • October 2024: the Tropicana is demolished. GLPI later sets aside $125 million left over from the demolition for Bally's district.
  • May 2026: there is talk of a temporary plaza in case Bally's financing lags.
  • August 2026: Bally's commits to building the podium and says it is in the final stages of financing.
  • November 4, 2026: at a Stadium Authority meeting, Bally's is still securing funding; GLPI offers conditional money; the A's present contingency plans.
  • December 3, 2026: Stadium Authority meeting on the northwest plaza entrance.
  • December 2026: the A's decision point on a temporary plaza.
  • January 2027: Bally's latest start date to finish by early 2028.
  • June 2027: permit deadline for a temporary plaza, per the A's.
  • 2028: the ballpark opens, with construction scheduled to finish by February 29, 2028.

The Bottom Line

The A's front door depends on a deal the public has not seen. GLPI has the money set aside and has signaled it could double it, Bally's says it needs to break ground by January, and the A's are preparing a fallback. The December 3 Stadium Authority meeting is the next real checkpoint. We will update this page when it happens.

Sources

The LV Athletics is an independent, fan-run site and is not affiliated with Major League Baseball or the Athletics organization.

Tickets & Gear

Find Las Vegas A's tickets and gear through our affiliate partners. Purchases made through these links support independent coverage at no extra cost to you.

Fan FAQ

Frequently Asked Questions

Who is building the plaza at the A's Las Vegas ballpark?

Bally's Corp., which leases the land around the ballpark from Gaming and Leisure Properties (GLPI). The plan is a multilevel podium with a three-level parking garage topped by a plaza with retail, dining and entertainment at the northwest corner, the main entrance from the Strip.

How much money has GLPI offered for the plaza?

GLPI has $125 million set aside and told the Las Vegas Stadium Authority it was conditionally willing to increase that to $250 million. The condition is that Bally's and the A's settle a couple of business items that have not been made public.

When does the plaza need to start construction?

Bally's says it needs to start by January 2027 to finish comfortably in the first quarter of 2028. Its senior vice president of development, Nick Tomasino, called the plaza entry about a 12-month process.

Will the A's build a temporary plaza?

Possibly. The A's have contingency plans for a temporary plaza about 38 feet below the main entrance, with escalators and elevators up to the door. Senior advisor Sandy Dean said the team needs to decide in December and have permits by June 2027.

What happens at the December 3 Stadium Authority meeting?

The Las Vegas Stadium Authority meets to address the northwest plaza entrance. Chairman Steve Hill said that by the December meeting the board wants a clear and unconditional path to having the plaza ready when the ballpark opens.

Does the plaza fight delay the A's ballpark?

Not so far. The plaza is a separate project from the stadium, which the Review-Journal reported was just over 50 percent complete and on schedule for 2028 in mid-November 2026. The plaza decision affects what fans walk through on Opening Day.

Keep Reading

More Coverage

What Was on the A's Stadium Site Before? The Tropicana's Vegas History, Las Vegas Athletics stadium watch
Stadium Watch
What Was on the A's Stadium Site Before? The Tropicana's Vegas History
November 7, 2026
Will an MLB Lockout Delay the A's 2027 Season and the Las Vegas Move?, Las Vegas Athletics stadium watch
Stadium Watch
Will an MLB Lockout Delay the A's 2027 Season and the Las Vegas Move?
November 2, 2026
The A's New Las Vegas Ballpark: What Fans Should Know, Las Vegas Athletics stadium watch
Stadium Watch
The A's New Las Vegas Ballpark: What Fans Should Know
September 6, 2026